Continuous, real-time data used to reduce DPM levels

This case study shares the journey of the SMP4 Joint Venture during their construction of the TELT (Lyon to Turin) tunnel. By using fixed DPM monitors it was possible to gather data on the average base load.  Peak loads of 180 μg/m3 were reduced to 50 μg/m3 through the application of ventilation changes.

Continuous, real-time data used to reduce DPM levels